‘Probe cost increase in road projects by CID’
Related
Top Stories
- Trouble mounts for Sreesanth as Mumbai cops gather more evidence
- SIT to seek Supreme Court guidance on Maya Kodnani death penalty issue
- Tamil Nadu police bans Yasin Malik-linked pro-Eelam public meeting
- Kings XI Punjab end IPL 2013 campaign with a win
- Narendra Modi: India losing sheen as agricultural nation
Days after a comptroller and auditor general (CAG) report slammed BMC for cost escalations in road projects, opposition parties created uproar at a civic statutory standing committee meeting Friday demanding a CID inquiry against the ruling Sena-BJP alliance.
The CAG report tabled in the winter session of the legislative assembly claimed financial mismanagement on the part of the civic body, causing major revenue loss.
"There was no transparency in granting road contracts. The road repair and construction work is also of poor quality. The CAG report proves this," said Congress corporator and opposition leader Dnyanraj Nikam.
Samajwadi Party corporator Rais Shaikh said variation in tenders alloted by BMC showed high level of corruption.
"There should be a CID inquiry, specifically into the approval last year of road contracts of such huge variation."
The Shiv Sena-BJP alliance sought to shift part of the blame to the civic administration, stating the proposals were brought before the standing committee and members passed them.
"The proposals were passed by consent of all members, including opposition. None of the corporators protested or argued against," said Rahul Shewale, standing committee chairman and Shiv Sena corporator.
He claimed the CAG report seemed unlawful.
Another Sena corporator Yashodhar Phanse released names of then opposition corporators who had sought additional works in wards before civic elections.
"The road works carried out on demand also caused cost escalation. Why is the opposition not demanding an inquiry against its own senior leaders," he asked.
Meanwhile, the civic administration has decided to not include additional work in tenders to avoid cost escalation. It will also not undertake work outside the scope of an order passed in the committee.
"Earlier, we would carry out work other than proposed in a tender if needed. At times, money allotted for a project was in excess and we could undertake additional work. We will now stop these practices to prevent variation in road projects," said Aseem Gupta, additional municipal commissioner.
Editors’ Pick
- Destitute, orphan students outclass rest in Andhra Class 10 exams
- To re-energise ties, PM wants to visit US, waits for confirmation
- NIA court says no terror link, frees 'Hizbul militant' Liyaqat on bail
- CBI arrests its coal allotments investigator on bribery charge
- ‘Cricketer-bookie Amit may have used Jiju to reach Sree’
- BCCI chief N Srinivasan says police must prove spot-fixing allegations
- As it all sinks in, Sreesanth breaks down in tears, 'accepts mistake'


Teen raped at birthday party, sold to man
Alleged bomb planter Siddiqui claims ATS threatened to kill him
Cops pin hopes on CCTV footage to arrest acid attack accused
BMC single window to help people check legality of flats