After 5 yrs of delay, Jharkhand’s first expressway hits new roadblocks

Font Size
Manoj Prasad Posted: May 10, 2008 at 2311 hrs IST
Related Stories: Jharkhand: steel Co workers assaulted, industry calls for stirJMM bribery case returns to haunt Shibu SorenAnti-defection petitions: HC rap for J’khand SpeakerCM house gets facelift for SorenRTI plea shows Soren, Razi used state aircraft for private outings
RANCHI, MAY 9: The work on this road — the state Government-sponsored first six-lane expressway — is progressing at a snail’s pace. Construction work took five years to start after the inauguration. Still, there are many roadblocks that it faces.

Billed as Ring Road on the outskirts of the town, it has been divided into seven sections, entailing a total of 85.089 km.To begin with, its one section of 22.981 km is being built for the state Government at an estimated cost of Rs 203 crore by New Delhi-based Som Datt Builders Pvt Ltd (SDBPL) and Shrinet and Shandilya Construction Pvt Ltd (SSCPL). Once this section is complete, every single vehicle moving on NH-75 to enter NH-33 can zip off without getting caught in the traffic snarls of Ranchi town. “It will give a joyride to all those using it,” says Rajan Kumar, the project manager.

The expressway project was conceived by the NDA Government and inaugurated by Lal Krishna Advani on November 15, 2002. Five years later, a global tender was floated, and the construction work started after the state Government and the SDPL-SSPCL signed an agreement on June 5, 2007.

Ads By Google
However, to check the quality of work being carried out by the companies, the Singapore-based HSSI and VKS Infratech Management Pvt Ltd, roped in by the state road construction department (RCD), and set up a lab near the site.

And this is what the report, prepared by RCD after reviewing the progress till April 5, states:

A dozen electric poles carrying high-tension wire that were supposed to be removed by the Jharkhand State Electricity Borad continue to cause hindrance

Dimensions shown in drawings are contradictory

Dimension of median kerb shown in contract drawing is not correct

Anti-land acquisition groups are coming in the way of execution of work due to non-payment against their land acquired

“We will stall the construction work if we are not paid the money by the end of this month,” said Mukesh Manjhi, secretary of Sarna Samiti. Asked why the people were not paid compensation for the land acquired, Secretary (RCD) N N Sinha said the implementation work was launched after the land was acquired and compensation was paid to almost every legitimate owner. But in case of those who had not furnished bonafide land records, scrutiny was being made. “Very soon their problem will be sorted out,” he said.

Factsheet

Project conceived by NDA Govt in 2002

Inaugurated on Nov 15, 2002

Date of award of global bid: June 5, 2007

Work commenced on June 28, 2007

Date of completion of work: June 27, 2010

Ads By Google
Post Comments
Message*
Maximum characters allowed     
 
Name* Email ID*
Subject* Country*
TERMS OF USE:
The views, opinions and comments posted are your, and are not endorsed by this website. You shall be solely responsible for the comment posted here. The website reserves the right to delete, reject, or otherwise remove any views, opinions and comments posted or part thereof. You shall ensure that the comment is not inflammatory, abusive, derogatory, defamatory &/or obscene, or contain pornographic matter and/or does not constitute hate mail, or violate privacy of any person (s) or breach confidentiality or otherwise is illegal, immoral or contrary to public policy. Nor should it contain anything infringing copyright &/or intellectual property rights of any person(s).
I agree to the terms of use.
View all Messages [ 0 ]
View all Messages [ 0 ]
Group Websites : Express India | Financial Express | Screen India | Loksatta | Kashmir Live | Biz Publications
Privacy Policy | Feedback | Site MapThe Indian Express Group | Work With Us | Adverise With Us | Contact Us© 2009 Indian Express Newspapers (Mumbai) Ltd. All rights reserved
*Recipient(s) name *
*Recipient(s) e-mail address *
(Separate addresses by commas)
*Your Name *
*Your e-mail address *
Select your Country
Comments(optional)

The name(s) and e-mail address(es) you provide will
not be used for any purpose other than to inform the
recipient(s) of your identity. (*mandatory field)
 
Close