Premium
This is an archive article published on August 5, 2010

BRO bridge collapse: Probe zeroes in on design fault

Preliminary inquiry into the collapse of the one-year-old bridge on the Nauti Khud rivulet last week has started zeroing in on design fault.

Preliminary inquiry into the collapse of the one-year-old bridge on the Nauti Khud rivulet last week has started zeroing in on design fault. The bridge built by the Border Roads Organisation (BRO) under its Deepak Project on the Basantpur-Kingal-Rampur Road,50 kilometres from Shimla,gave way when four cement laden trucks were parked on it on June 28.

Initial inquiries have raised more doubts on the design of the bridge than the material used in construction,considering the peculiar manner in which the top part of the bridge had toppled over from the base structure and tilted to one side,unable to take load of the trucks.

The Deepak Project headquarters at Shimla have now approached the state’s public works department to get data on similar ‘single span curved bridges’ in other parts of the state for a comparative study of the designs.

Story continues below this ad

The bridge was classified as ‘Road Class 7’ with a load-bearing capacity of 70 tonnes. The load of the trucks parked on the bridge was also assessed as almost equal; but the bridge collapsed,killing two persons and injuring two.

The bridge is on the strategic all-weather Shimla-Basantpur-Kingal-Rampur-Kinanur Road that connects the state with the Indo-Tibetan border in Kinnaur district.

“I cannot comment on the possible causes of the collapse,as our internal inquiry is yet to study all the aspects in detail. The top platform-road surface area of the bridge has toppled and tilted to one side due to concentration of weight on the outer side of the bridge’s curve and there is no damage to the sub-structure (support structure pillars) or cracks on the surface. Many aspects,including design,are to be studied in detail,” said Director,Bridging and Tunnels,A K Dikshit (Superintending Engineer,Civil,at BRO DG office in New Delhi).

Dikshit left for Delhi on Wednesday after visiting the site.

Story continues below this ad

The 45-metre long and 12-metre wide (including the footpath) bridge was constructed with an approximate cost of Rs 1.85 crore. After successful trials,the bridge was commissioned in October 2010. “The bridge will certainly require reconstruction after required approvals,” said I R Mathur,Chief Engineer,Deepak Project (Headquarters).

Stay updated with the latest - Click here to follow us on Instagram

Latest Comment
Post Comment
Read Comments
Advertisement
Loading Taboola...
Advertisement