According to sources, the cash-strapped road development corporation has to recover Rs 2,300 crore from the state government. Sources also add that MSRDC has stopped payment of contractors for several projects across the state and unless grants from the state government are extended, major projects could be in jeopardy.
Bill and breakup
Rs 1,634 crore: Overall project
Rs 580 crore: Government grant
Rs 150 crore: MMRDA loan
Rs 500 crore: Bank loans
Rs 76 crore: From bonds
Rs 328 crore: Escalation, no decision yet on how to raise it