Govt can't cancel Jindal contract: Ex-SG
Related
Top Stories
- IPL spot-fixing case: Net widens, police watching 3 more players, other bookies
- IPL 2013: Imperious Brad Hodge powers Rajasthan Royals to qualifier
- Sonia Gandhi, PM Manmohan Singh slam BJP for disrupting Parliament, stalling bills
- IPL spot-fixing: 'Bookie' Vindoo was close to BCCI chief's son-in-law, say cops
- Jessica Lall case: Shayan Munshi to face perjury trial

The government cannot terminate oil and gas field contract of a company that has defaulted on its obligations like furnishing of bank guarantees, former Solicitor General Gopal Subramanium has said.
The Directorate General of Hydrocarbon (DGH) has sought his views on Jindal Petroleum Ltd's (JPL) failure to fulfil its legal requirements like submission of bank guarantee for block RJ-ONN-2005/1 in Rajasthan.
Jindal, Hindustan Oil Exploration Company (HOEC), Bharat PetroResources Ltd and IMC Ltd held 25 per cent apeice in the block for which a Production Sharing Contract was signed on December 22, 2008.
While other companies fulfilled their legal obligations,
Jindal defaulted by not submitting the bank guarantee, a financial and performance guarantee and legal opinion within 30 days to become the contractor.
DGH's legal head Simran Dhir on September 21 wrote to Joint Secretary (Exploration) in Oil Ministry that DGH as had been instructed by the ministry, had taken a legal opinion from Subramanium.
Subramanium has opined that Jindal Petroleum has become a contractor despite failing to fulfil its requirements of the PSC, Dhir wrote.
On query if Government can terminate the PSC qua the defaulting contractor and auction the share of the defaulting contractor to any other party, the former solicitor general has opined in negative, the letter said.
On the issue of the share of defaulting contractor (JPL) vesting in the government, Subramanium opined in negative. "However, if all the contracting parties default, the
Government can terminate the PSC," Dhir wrote citing the legal opinion.
Subramanium in his opinion stated that failure to meet legal obligations "does not mean that JPL is not a party to the PSC or a contractor company... The PSC expressly recognises every signatory to that contract as a contractor company."
He went on to state that his "opinion is being rendered on the supposition that only one contracting party has defaulted. Needless to say, if all the contracting parties
... contd.
Editors’ Pick
- Paddy shortfall blamed for mystery death of procurement officer
- 'Bookie' Vindoo was close to BCCI chief’s son-in-law: cops
- Net widens, police watching three more players, new set of bookies
- Suspected Islamists behead soldier on London street
- Malegaon 2006 case: NIA names four right wing terror suspects
- BJP invokes 'sarcasm, ridicule' against PM
- Nine years on, Sonia, PM put up show of unity, Singh hints at unfinished business


After lull, highway projects see aggressive bid offers
Govt aims to bring down CAD to 2.5% by 12th Plan-end, says Montek
Raghuram Rajan not in favour of sovereign bond to finance CAD
Companies expand background check on jobseekers