Only 47 per cent of the schemes taken up under MGNREGA were completed in 2009-10 in Jharkhand, says the CAG report.
"...Out of a total 1,60,813 schemes only 75,767 schemes completed at the end of 2009/10," said the CAG report for the year ended March 31, 2001, which was placed during the recently concluded monsoon session of the assembly.
"Out of a total available funds of Rs 1916.29 crore only Rs 1379.70 crore was spent¿Rs 188.05 crore was released in the last month of the financial year which affected the progress of the schemes," the report added.
The CAG also pointed out that only 31 per cent of schemes under Indira Awas Yojana were completed with only 94032 out of a total of 303684 schemes being completed in 2009/10.
Stating that only Rs 398.08 crore of Rs 647.12 crore were spent under these schemes, the CAG said that non-achievement of targets had deprived people residing below the poverty line of the intended benefits despite the availability of funds.
Editors’ Pick
- Fixing probe now reaches Bollywood, son of Dara Singh held
- BCCI cashes Pune guarantee, Sahara walks out of IPL
- 'Sree spent Rs 1.95L on clothes, bought friend BlackBerry'
- Delhi firm with MoD as client is linked to Pak cyberattacks
- After Infosys, iGATE sacks Phaneesh Murthy for sexual misconduct
- 2 weeks after harassment, Haryana schoolgirls return, cops in tow
- UPA-2 anniversary today, to showcase achievements of UPA-1


For once, Cong compares Rahul, Modi
Congress wins power in Karnataka, BJP crushed
Heart of coal report changed, says SC
Happy over defeat of anti-Marathi Karnataka govt: Uddhav Thackeray