However, it is learnt that the NHAI, after receiving a formal request for modifications, has not agreed to undertake the exercise, as the highway was already being upgraded under the NHDP III programme. Instead, they are expected to ask NTPC to deploy more trucks and have standby trailers to ensure this machinery gets off the ghat section. However, NHAI has agreed to cut some of the rocks to allow this machinery to pass through.
Deployment of these additional specialised trailers is expected to take time. There will be also be several trucks and trailers moving at very slow pace, and the state Government would have to agree to restrict traffic movement on this route for a few days, failing which there would be severe traffic jams.
Sources said the final decision on when and how the power machinery moves forward and reaches the plant site in Chhattisgarh rests with the Maharashtra Government.