After 5 yrs of delay, Jharkhand’s first expressway hits new roadblocks

Print Email Feedback Discuss
Rate Article
Rating:  
Manoj Prasad Posted: May 10, 2008 at 2311 hrs IST
RANCHI, MAY 9 The work on this road — the state Government-sponsored first six-lane expressway — is progressing at a snail’s pace. Construction work took five years to start after the inauguration. Still, there are many roadblocks that it faces.

Billed as Ring Road on the outskirts of the town, it has been divided into seven sections, entailing a total of 85.089 km.To begin with, its one section of 22.981 km is being built for the state Government at an estimated cost of Rs 203 crore by New Delhi-based Som Datt Builders Pvt Ltd (SDBPL) and Shrinet and Shandilya Construction Pvt Ltd (SSCPL). Once this section is complete, every single vehicle moving on NH-75 to enter NH-33 can zip off without getting caught in the traffic snarls of Ranchi town. “It will give a joyride to all those using it,” says Rajan Kumar, the project manager.

The expressway project was conceived by the NDA Government and inaugurated by Lal Krishna Advani on November 15, 2002. Five years later, a global tender was floated, and the construction work started after the state Government and the SDPL-SSPCL signed an agreement on June 5, 2007.

However, to check the quality of work being carried out by the companies, the Singapore-based HSSI and VKS Infratech Management Pvt Ltd, roped in by the state road construction department (RCD), and set up a lab near the site.

Ads By Google

Related Stories:

And this is what the report, prepared by RCD after reviewing the progress till April 5, states:

A dozen electric poles carrying high-tension wire that were supposed to be removed by the Jharkhand State Electricity Borad continue to cause hindrance

Dimensions shown in drawings are contradictory

Dimension of median kerb shown in contract drawing is not correct

Anti-land acquisition groups are coming in the way of execution of work due to non-payment against their land acquired

“We will stall the construction work if we are not paid the money by the end of this month,” said Mukesh Manjhi, secretary of Sarna Samiti. Asked why the people were not paid compensation for the land acquired, Secretary (RCD) N N Sinha said the implementation work was launched after the land was acquired and compensation was paid to almost every legitimate owner. But in case of those who had not furnished bonafide land records, scrutiny was being made. “Very soon their problem will be sorted out,” he said.

Factsheet

Project conceived by NDA...

Post Comments
Message*
Maximum characters allowed     
 
Name* Email ID*
Subject* Country*
TERMS OF USE:
The views represented here are not neccesarily endorsed by www.expressindia.com and its allied websites. All messages will be moderated and no message that has inflammatory, abusive, derogatory language or any language deemed unfit for publication by the editor will be displayed. Though it will be endeavoured that as many messages as possible be displayed, there will be time lag between the submission and publication of the messages. The website reserves the right to publish or reject any message.
I agree to the terms of use.
View all Messages [ 0 ]
Group Websites : Express India | Financial Express | Screen India | Loksatta | Kashmir Live | Biz Publications
Privacy Policy | Feedback | Site MapThe Indian Express Group | Work With Us | Adverise With Us | Contact Us© 2008 Indian Express Newspapers (Mumbai) Ltd. All rights reserved
*Recipient's name *
*Recipient's e-mail address *
(multiple addresses by commas)
*Your Name *
*Your e-mail address *
Select your Country
Comments(optional)

The name's and e-mail address'es you provide will not
be used for any purpose other than to inform the
recipient's of your identity. (*mandatory field)
 
Close