In April & June, Centre reminded Bihar of Kosi’s unfinished work

Font Size
J P Yadav Posted: Aug 30, 2008 at 0209 hrs IST
Related Stories: Nepal, India to reconstruct Kosi river embankmentMove SC if you don’t want Kosi panel: Bihar to CentreBirpur engineers left out of Kosi breach repair workBihar scuttles Centre probe into Kosi breachKosi: who will plug Govt breach?Nitish deploys e-mails, camera phones to counter flood charges
New Delhi, August 29: In the 48 hours preceding the breach in the Kosi embankment, the Bihar government’s Water Resources Department had twice declared that “all embankments” maintained by it were “safe”.

In two pre-flood bulletins issued on August 16 and August 17, the Department said: “Jal Sansadhan vibhag ke antargat sabhi tatbandh surakshit hain (All embankments...are safe).”

On August 18, the Kosi smashed the embankment at Kusaha in Nepal, supposed to have been repaired and maintained by the Bihar government. But records show that the Centre, which reimburses Bihar’s cost on the works, repeatedly wanted to know from the state what preventive action was being taken on the Kosi in Nepal.

On April 1, the Patna-based Director (Coordination) of the Ganga Flood Control Commission— a body under the Union Ministry of Water Resources— wrote to the Engineer-in-Chief (North) of Bihar’s Water Resources Department. The letter clearly asks the state to specify what is being done “on river Kosi in Nepal portion based on the recommendations of Kosi High Level Committee for the protection works to be executed before the floods of 2008.” And that it send a report “immediately to this office for taking necessary action.”

Ads By Google
The same lines were repeated in two subsequent letters, dated April 25 and June 12. Copies of all three letters are available with the Indian Express.

Union Minister of State for Water Resources Jaiprakash Narayan Yadav says the Bihar Government did not reply to any letter.

Bihar Water Resources Minister Bijeyndra Yadav acknowledged that no schedule of repairs or estimates of costs was submitted to the Centre. “Kal bhej rahe hain (We are sending it tomorrow),” he told The Indian Express over the phone. He said that “anti-erosion work” was done.

Sources said local people chased away state engineers when they went to repair the breach on August 18, saying they would not now be allowed to do something they should have done earlier.

Ads By Google
Post Comments
Message*
Maximum characters allowed     
 
Name* Email ID*
Subject* Country*
TERMS OF USE:
The views, opinions and comments posted are your, and are not endorsed by this website. You shall be solely responsible for the comment posted here. The website reserves the right to delete, reject, or otherwise remove any views, opinions and comments posted or part thereof. You shall ensure that the comment is not inflammatory, abusive, derogatory, defamatory &/or obscene, or contain pornographic matter and/or does not constitute hate mail, or violate privacy of any person (s) or breach confidentiality or otherwise is illegal, immoral or contrary to public policy. Nor should it contain anything infringing copyright &/or intellectual property rights of any person(s).
I agree to the terms of use.
View all Messages [ 0 ]
View all Messages [ 0 ]
Group Websites : Express India | Financial Express | Screen India | Loksatta | Kashmir Live | Biz Publications
Privacy Policy | Feedback | Site MapThe Indian Express Group | Work With Us | Adverise With Us | Contact Us© 2008 Indian Express Newspapers (Mumbai) Ltd. All rights reserved
*Recipient(s) name *
*Recipient(s) e-mail address *
(Separate addresses by commas)
*Your Name *
*Your e-mail address *
Select your Country
Comments(optional)

The name(s) and e-mail address(es) you provide will
not be used for any purpose other than to inform the
recipient(s) of your identity. (*mandatory field)
 
Close